| SES # | TOPICS | 
|---|---|
| 1 | Production Chosen | 
| 2 | 22 Weeks to Opening 1st Design Meeting  | 
| 3 | 20 Weeks to Opening 2nd Design Meeting  | 
| 4 | 18 Weeks to Opening 3rd Design Meeting  | 
| 5 | 16 Weeks to Opening 4th Design Meeting - Presentation  | 
| 6 | 15 Weeks to Opening | 
| 7 | 14 Weeks to Opening 1st Production Meeting  | 
| 8 | 14 Weeks to Opening | 
| 9 | 13 Weeks to Opening | 
| 10 | 11 Weeks to Opening 2nd Production Meeting  | 
| 11 | 11 Weeks to Opening | 
| 12 | 10 Weeks to Opening | 
| 13 | 10 Weeks to Opening | 
| 14 | 8 Weeks to Opening 3rd Production Meeting  | 
| 15 | 4 Weeks to Opening | 
| 16 | 4 Weeks to Opening | 
| 17 | 4 Weeks to Opening 4th Production Meeting  | 
| 18 | 3 Weeks to Opening 5th Production Meeting  | 
| 19 | 2 Weeks to Opening 6th Production Meeting  | 
| 20 | 2 Weeks to Opening | 
| 21 | 1 Week to Opening 7th Production Meeting  | 
| 22 | 6 Days before Opening | 
| 23 | 5 Days before Opening | 
| 24 | 4 Days before Opening | 
| 25 | 3 Days before Opening | 
| 26 | 2 Days before Opening | 
| 27 | 1 Day before Opening | 
| 28 | Opening | 
| 29 | Performance Week 1 | 
| 30 | Performance Week 2 |